Safe Harbor compliance at 700+ MW
IRS Notice 2025-42 made the Physical Work Test the only Beginning of Construction pathway above 1.5 MW. Developers who had relied on spend records now needed physical evidence on file for every project.
- Role
- Lead Strategist & Engagement Director
- Firm
- SafeHarbor Partners
- Portfolio
- 700+ MW solar, wind and hybrid
- Scope
- Sold the engagement, then governed it
What changed
Utility-scale renewable projects qualify for federal tax credits based on when construction began. Developers historically had two ways to establish Beginning of Construction: demonstrate physical work of a significant nature, or show they’d incurred 5% of total project cost. Most developers used the second, because it is a spreadsheet exercise.
IRS Notice 2025-42 eliminated the 5% spend test for projects above 1.5 MW, leaving the Physical Work Test as the only pathway.
Why that’s harder than it sounds
A spend test either clears or it doesn’t, and you know the number in advance. A physical work test is a documentary argument, assembled across field crews, EPC contracts and supply chain records, built months or years before anyone audits it, by people who have no idea what an auditor will eventually ask them for.
What I owned
Selling it
I ran the cycle from first outreach to signed agreement. These were consultative conversations with developers, their counsel and their investors in the room, where the product was judgment and the real buying decision was whether your documentation will survive scrutiny several years from now. You establish that in discovery or you don’t establish it.
Writing the standard
I established and enforced the firm-wide governance protocols and SOPs for Physical Work Test documentation, and acted as central policy authority across every institutional audit package. It was centralised because if each file interprets the standard slightly differently, the firm doesn’t have a defensible position, it has a collection of opinions that happen to be filed together.
Running the files
A cross-functional team of strategists and field coordinators across concurrent engagements, each carrying multi-million-dollar client value. I coordinated with CPA firms, tax attorneys and institutional tax equity investors on ITC/PTC eligibility, FEOC supply chain compliance and domestic content adder qualification, plus direct work with Novogradac and Baker Tilly on financial model alignment and investor-ready reporting.
Absorbing the shocks
Twice, serious problems came up mid-engagement: FEOC supply chain exposure on one file and EPC scope changes on another. Both got identified and resolved without delivery delay and without any file losing credit eligibility. Catching them early is a direct function of having a protocol that forces the same questions onto every file, rather than depending on who happened to be reviewing that week.
What selling this taught me
Institutional buyers are paying for confidence that the document will hold up, from someone who will still be reachable when it’s tested. That reframing changed how I run discovery on everything now, including $10K engagements with no tax equity at risk.
Where it landed
- Solar, wind and hybrid across concurrent engagements
- 700+ MWSolar, wind and hybrid across concurrent engagements
- Compliance held and credit eligibility preserved on every file
- 100%Compliance held and credit eligibility preserved on every file
I kept this alongside the automation work deliberately. On Monday I might be taking people out of a lead queue, and on Tuesday writing a protocol whose purpose was to prove a person checked. Switching between the two taught me to ask early which kind of problem I’m looking at.